Registering a project with MahaRERA: the document set that avoids a query
Registration files are rarely rejected outright. They are queried — and each query costs a fortnight. Almost all of it is avoidable by assembling the bundle properly before the first submission.
The core bundle
- Title report from an advocate, with the full chain of title and any encumbrances disclosed.
- Sanctioned plans, layout approvals and the commencement certificate as issued.
- The declaration on the project completion date, phasing and the separate project account.
- Promoter constitution documents — LLP agreement or memorandum, PAN, and authorised-signatory proof.
- Proforma of the allotment letter, agreement for sale and conveyance deed.
Where files come back
- A title report that notes an encumbrance in the body but omits it from the summary.
- Plans that do not reconcile with the built-up numbers declared elsewhere in the application.
- A completion date chosen optimistically, with no internal basis for it.
The declared completion date is the one commitment you will be measured against for years. Choose it as a construction decision, not a marketing one.
Assemble once, reconcile across documents, then file. The extra week at the start is the cheapest week in the project.
More reading
An agent's records and advertisements: what MahaRERA expects to see
Registration is the beginning. The obligations that follow are the ones agents are actually penalised for missing.
The 2026 MahaRERA QPR calendar every promoter needs
Quarterly Progress Reports are where good projects quietly slip into default. Here is the year-round calendar — and the disclosures that trip promoters up most.
Form 5 and the project account: what the annual RERA audit really tests
The 70% rule is simple to state and easy to breach. The annual audit is where withdrawals meet the construction actually certified as complete.